El Dorado County Grand Jury • 2016-2017

El Dorado County Legacy Application Migration and Mainframe Decommissioning Success(PDF, 1004kb)

Published: June 09, 2017 11 pages
View Original PDF

Findings 6 findings

F1
Absent an IT strategic plan, supported by the BOS and senior leadership of EDC, the IT department lacks solid direction and the ability to manage projects to successful completion.
F2
EDC has a complex IT operating environment, created by using multiple platforms (software and hardware), that requires diverse IT skills sets and is expensive to maintain.
F3
Having the IT functions decentralized provided an uncoordinated leadership that has created complexity, the risk to operations and increased operating costs.
F4
The lack of a single senior, professional, Chief Information Officer (CIO) with county-wide IT responsibility has created an environment where department heads set policy and direction at odds with county-wide priorities and needs.
F5
The lack of support from various departments for the IT migration project creates roadblocks to IT’s success.
F6
Elected Officials functioning as Departments Directors that are not accountable to the BOS or CAO cannot be required to comply with the demands of the application migration. Mainframe Decommissioning Success Challenged by EDC Organization and Management

Recommendations 4