San Francisco County Grand Jury
• 2024-2025
Building San Francisco - Full ReportThis report details the Jury's research, investigation, findings, and recommendations.PublishedJune 20, 2024
⚠️ Translation Notice: This content has been automatically translated. The original English text is the official version. Translation may contain errors.
⚠️ Este contenido ha sido traducido automáticamente. El texto original en inglés es la versión oficial. La traducción puede contener errores.
Findings and Recommendations 4 findings
F1
The Amount of Degraded Assets is Unknown...........................................................25
Related Recommendations (1)
R1
1 By March 31, 2025, the Controller shall conduct a financial analysis of the additional cost to the city entailed by delaying full repair of “degraded facilities assets” and issue the report to the Mayor, the Board of Supervisors, and publish the report to the public.
F2
Capital Facilities Projects Require More Accountability and Oversight...................26
Related Recommendations (1)
R2
3, R2.4, R2.5, R2.8,
F3
Completed Capital Facilities Projects Require Auditing............................................28
Related Recommendations (1)
R3
3, R3.4, R3.5 Capital Planning Committee F1 R1.4 Public Works Commission F1, F2 R2.6, R2.7, R2.9,
F4
Department of Public Works Needs to Educate Other Departments about How It Calculates Labor Costs................................................................................................................29
Related Recommendations (1)
R4
Controller F1, F3 R1.1, R3.1, R3.2,