12 responses to findings and recommendations
F1
The 2022-2023 Grand Jury reviewed responses to five of the 2019-2020 reports and found that, in general, commitments were kept. _X_ AGREE __ PARTIALLY DISAGREE __ DISAGREE Response explanation (required for a response other than Agree):
Response: Unknown
Score: 0
R1
All agencies should provide their own independent responses to findings and recommendations instead of referring to the response of another agency. (F2) __ HAS BEEN IMPLEMENTED – summarize what has been done HAS NOT YET BEEN IMPLEMENTED BUT WILL BE IN THE FUTURE – __ summarize what will be done and the timeframe REQUIRES FURTHER ANALYSIS – explain the scope and timeframe __ (not to exceed six months) _X_ WILL NOT BE IMPLEMENTED – explain why
Response: Unknown
Score: 0
F2
The evident coordination of responses from agencies leaves the public without independent contributions across agencies. __ AGREE __ PARTIALLY DISAGREE _X_ DISAGREE Response explanation (required for a response other than Agree): When an agency agrees with the response of another agency or coordinates with another agency, the positive interpretation of that could be that there is synchronization and agreement of content – be that approach, subject matter expertise, next steps, etc. This alignmen...
Response: Disagree Partially
Score: 0
. With the planned growth of UCSC to 28,000 students, the potential demand for off campus housing for students, faculty and staff has the potential to make the affordable housing problem even worse. _X_ AGREE __ PARTIALLY DISAGREE __ DISAGREE Response explanation (required for a response other than Agree): Thus, it is critical for UCSC to provide on-campus housing for its growing student body and accompanying faculty and staff. F12. While all local municipalities have voiced support for prioritizing housing for local workers, only some of them have clear local preference guidelines that give s...
R2
We continue to recommend that all organizations create and regularly update formal records of the actions they take to address Grand Jury recommendations, and to share those records with the public, in accordance with CA Penal Code Section 933(c). (F1, F2) __ HAS BEEN IMPLEMENTED – summarize what has been done HAS NOT YET BEEN IMPLEMENTED BUT WILL BE IN THE FUTURE – __ summarize what will be done and the timeframe REQUIRES FURTHER ANALYSIS – explain the scope and timeframe __ (not to exceed six ...
Response: Unknown
Score: 0
F3
The City of Santa Cruz delayed the timeline rather than proceeding as outlined in their 2020 response to the Grand Jury. Instead, the City budgeted for a more comprehensive assessment of system-wide facilities and a capital investment plan to be completed in 2023. __ AGREE __ PARTIALLY DISAGREE _X_ DISAGREE Response explanation (required for a response other than Agree): The Parks & Recreation Department has evaluated the condition of the driving range/cart barn and requested capital investment ...
Response: Unknown
Score: 0
R3
The City of Santa Cruz should report to the Grand Jury on the completion status of the Facilities Assessment and capital investment plan no later than December 31, 2023. (F3) __ HAS BEEN IMPLEMENTED – summarize what has been done HAS NOT YET BEEN IMPLEMENTED BUT WILL BE IN THE FUTURE – _X_ summarize what will be done and the timeframe REQUIRES FURTHER ANALYSIS – explain the scope and timeframe __ (not to exceed six months) __ WILL NOT BE IMPLEMENTED – explain why
Response: Unknown
Score: 0
F5
The adoption of multi-year plans by both the City and County of Santa Cruz offer the public some assurance that locations can be found within the County where homeless services will be provided. _X_ AGREE __ PARTIALLY DISAGREE __ DISAGREE Response explanation (required for a response other than Agree):
Response: Unknown
Score: 0
R6
The County of Santa Cruz and the four cities should plan to provide services for homeless persons at the sites identified in their plans, including but not limited to supportive housing, case management, and medical services. The County of Santa Cruz and the four cities should report to the Grand Jury on the status of providing homeless services at the sites identified no later than December 31, 2023. (F5, F6) _X_ HAS BEEN IMPLEMENTED – summarize what has been done HAS NOT YET BEEN IMPLEMENTED B...
Response: Unknown
Score: 0
F7
The master plan for Coral Street being worked by the City of Santa Cruz includes consideration of limiting vehicle access to Coral Street, but the grants received by the City and the plan to build 120 units of supportive housing preempt the original Grand Jury recommendation to consider closing it. __ AGREE _X_ PARTIALLY DISAGREE __ DISAGREE Response explanation (required for a response other than Agree): A variety of uses exist on Coral Street. Vehicular access is needed to/from many of those r...
Response: Unknown
Score: 0
R7
The City of Santa Cruz should complete and then implement their Master Plan for Coral Street, including consideration of limiting vehicle access. The City of Santa Cruz should report to the Grand Jury on the status of Coral Street no later than December 31, 2023. (F7) __ HAS BEEN IMPLEMENTED – summarize what has been done HAS NOT YET BEEN IMPLEMENTED BUT WILL BE IN THE FUTURE – _X_ summarize what will be done and the timeframe REQUIRES FURTHER ANALYSIS – explain the scope and timeframe __ (not t...
Response: Unknown
Score: 0
F8
Staffing shortages made automating the process for updating the website of the City of Santa Cruz and redesigning the website of the City of Scotts Valley more difficult. __ AGREE _X_ PARTIALLY DISAGREE __ DISAGREE Response explanation (required for a response other than Agree): For the City of Santa Cruz, significant progress has been made in addressing staffing shortages within the IT Department, and continuous efforts are underway to enhance the City's website update procedures. These initiat...
Response: Unknown
Score: 0
R8
The City of Santa Cruz should verify that their commitment to automate the process for updating their website has been completed by October 31, 2023. (F8) _X_ HAS BEEN IMPLEMENTED – summarize what has been done HAS NOT YET BEEN IMPLEMENTED BUT WILL BE IN THE FUTURE – __ summarize what will be done and the timeframe REQUIRES FURTHER ANALYSIS – explain the scope and timeframe __ (not to exceed six months) __ WILL NOT BE IMPLEMENTED – explain why
Response: Unknown
Score: 0