San Mateo County Grand Jury • 2017-2018

Project Management of the Caltrain Modernization Program Issue | Summary | Glossary | Background | Discussion |

Published: July 18, 2018 57 pages
View Original PDF

Note: Missing finding numbers detected: F2

Findings and Recommendations 11 findings

F1
The CBOSS PTC project had several management failings as noted by the American Public Transportation Association (APTA) report. Among the Caltrain management issues noted by APTA were:  No commonly approved project schedule between Caltrain and Parsons  Lack of a strong in-house technical team to oversee the project  No commonly agreed upon definition of some final deliverables or how to test them  Lack of a working escalation method to resolve issues raised between Caltrain and Parsons
Related Recommendations (1)
R6
TECHNOLOGICAL: EFFECTIVENESS OF DESIGN In the view of the panel, animosities between the prime contractor and project management oversight present an impediment to resolving outstanding technical issues. PTG appears to have appropriate technical resources to complete CBOSS requirements for Caltrain running on Caltrain tracks. It is apparent that TASI resources have not been fully engaged during the course of the project. RE
F3
The CalMod project schedule process appears coordinated and integrated among the main contractors, consultants, and CalMod. The duties of the consulting firm of Gannett Fleming include schedule coordination.
No recommendations for this finding
F4
While membership in the Change Management Board is not completely settled, the board is evaluating and approving changes as they occur.
No recommendations for this finding
F5
CalMod’s Risk Assessment Committee (made up of representatives from funding partners and CalMod management) meets monthly to identify risks and mitigation measures. Progress in mitigating risks enumerated in the Program Risk Register is reviewed at this meeting and on an ongoing basis by the person employed as Risk Management Lead.
No recommendations for this finding
F6
CalMod appears to have an experienced Chief Officer and senior managers in place.
No recommendations for this finding
F7
Quality control and quality assurance processes appear to be functioning as designed.
No recommendations for this finding
F8
Caltrain has adequate management processes in place to implement a project of this scale.
No recommendations for this finding
F9
Most CalMod project information is available to the public, but it is not readily accessible to members of the public who do not know exactly where to look for it. It is difficult for the public to understand if the CalMod project is on budget and schedule without access to easily decipherable summary reports.
Related Recommendations (1)
R1
Caltrain should publish an interactive dashboard focusing on overall project schedule, budget, and deliverables that is readily visible on the CalMod homepage (calmod.org). The dashboard should include links to the supporting data in the Monthly Progress Reports and other places. This recommendation should be implemented
F10
Transportation agencies such as the Virginia Department of Transportation and LetsGoCT! use interactive project status dashboards to keep the public informed about their large and complex projects and budgets.
No recommendations for this finding
F11
The Monthly Progress Reports delivered to the PCJPB show total current expenditures compared to the overall budget. In particular, they show “Cost this Month” and “Cost to Date.” but do not show a budget timeline of current expenditures to planned expenditures on a monthly basis. Graphs showing draw downs on CalMod’s $315 million contingency fund that are provided to the PCJPB do not include a narrative explanation. Without a variance analysis and narrative, it is difficult for members of the public to understand why a deviation from the budgeted amount occurred.
No recommendations for this finding
F12
The summary information provided to the public regarding scheduling milestones in the body of Monthly Progress Reports is insufficient. The public cannot tell from that summary if CalMod is on schedule when the published milestone chart and the critical path charts in that summary have entries that have gaps as long as two years. The appendix to each Monthly Progress Report does contain more detailed schedule information in the form of a summary Master Program Schedule, but understanding it requires some knowledge of Gantt charts to fully understand the information.
Related Recommendations (1)
R3
A high-level CalMod project schedule should be published every month showing the progress of the project against the planned timeline. The schedule should have quarterly milestones so that the public can determine if the overall project is on schedule. This schedule should be included in the Executive Summary and Schedule sections of the Monthly Progress Reports. This recommendation should be implemented

Additional Recommendations 3

These recommendations are not explicitly linked to specific findings.

Conclusions 1

No Responses Found 1

Government entities assigned to respond to this report. No response documents have been linked in our database.

Peninsula Corridor Joint Powers Board Agency