Ventura County Planning Division Conditional Use Permit (cup) Process
⚠️ Aviso de traducción: Este contenido ha sido traducido automáticamente. El texto original en inglés es la versión oficial. La traducción puede contener errores.
⚠️ Este contenido ha sido traducido automáticamente. El texto original en inglés es la versión oficial. La traducción puede contener errores.
Findings 7 findings
F1
With 48 authorized positions, the Planning Division is responsible for Planned Development Permits, Subdivisions, General Plan Amendments, Variances, Zone Changes, and Appeals, in addition to processing CUPs.
F2
CUPs are required for projects considered to be "major," potentially controversial and impactive to surrounding uses. Time limits are placed on CUPs to review the continued consistency of use with surroundings, and to ensure that conditions are being followed and are still effective as originally designed.
F3
Requirements for approval have become much more complex in recent years.
F4
In 1995, action was taken for 24 CUPs. The time from completion of the application to action averaged just over 2 months. In April 1996, about 220 cases were in process.
F5
During 1995, 49 additional CUPs were in process. APPLICANT SUBMITTAL DATE CUP 1986 1 1987-1990 0 1991 1 1992 4 50 TOTAL 49
F6
In 1995, the average charges by the Planning Division for CUPs on which action was taken totaled $2336.90, with the highest charges being $16,418.50, and one free. Based on 1993-94 and 1994-95 data, the Planning Division estimates its time per transaction for a CUP to be 22 hours of County staff time. a. A chronology for the 1986 CUP submittal shows that an incomplete application for the 12th in a series of modifications over its 20 year history was filed one day before the previous CUP expired. b. In 1988 the California Environmental Quality Act (CEQA) was the basis for requiring an Environmental Impact Report (EIR). c. After significant delays, with three firms selected over several years to prepare the EIR, slow responses by the 1986 owner/applicant, inadequate and incomplete EIR submissions, time-consuming differences with the selected firms, interaction with the State Mining an Geology Board, withdrawal/refile letters from the applicant, requirements for revegetation and reclamation from the State Reclamation Unit, an Environmental Report Review Committee direction in October 1994 that (Planning) staff prepare the Preliminary Final EIR, and transfer of the assigned staff person to another branch of the County in June 1995, the Second Revised Draft EIR was submitted in March 1996. d. The current owner/applicant for the 1986 submittal purchased the business in 1993, with assurance from the Planning Director that operations could continue, though the previous owner was not in compliance on several matters. The County Zoning Ordinance allows continued processing of a CUP renewal request after its expiration, with development of a Compliance Agreement carrying forward the CUP conditions. e. The current owner/applicant reports payments of $99,258.39 for remediation and $666,738.47 for permitting through December 31, 1995. These are mainly charges payable to attorneys and vendors other than the County for required work. In 1996, this applicant paid $30,322.71 to the County and $23,742.22 in other costs related to securing the CUP, through February 24. f. A neighbor's 1990 lawsuit involving zoning restrictions and subsequent appeals were generally unsuccessful, with considerable costs in time and money for the litigants and the Planning Division.
F7
County officials concerned about the complexity of CUP approvals are working on ways to streamline the process. COMMENDATION The 1995/96 Grand Jury commends the Planning Division for their efforts to respond to the rapid proliferation of governmental requirements and regulations. 51
Recommendations 3
-
R1The Planning Division regularly review the CUP process to ensure that applicants and impacted individuals, groups and businesses receive prompt and appropriate action at minimal cost.
-
R2The Planning Division work with state and federal agencies to simplify CUP requirements and the approval process.
-
R3The Planning Division report to the Board of Supervisors semiannually on CUPs in process with estimated completion dates. The Planning Division appoint a task force for immediate attention to any application in process more than 6 months. RESPONSE REQUIRED Ventura County Planning Division 52