Extraído del Informe Consolidado

Esta investigación fue publicada originalmente como parte de un informe consolidado más amplio que contiene múltiples investigaciones. Consulte el PDF consolidado para ver el documento completo.

Lake County Grand Jury • 2005-2006

County Road Repair

View PDF View Full Original

Findings and Recommendations 4 findings

F1 Page 51
Road budget was $6,200,000 for the year 2004-2005. This year’s budget is $9,800,000.
No recommendations for this finding
F2 Page 51
The Board of Supervisors allocated $1,000,000 of the General County Fund to the Road Division.
No recommendations for this finding
F3 Page 51
The public Works Department anticipates receiving $400,000 in “guaranteed” funding from the Federal Transportation Program, however, these federal funds ARE NOT eligible to be used for our road maintenance but targeted for only new construction.
No recommendations for this finding
F4 Page 51
Employees should be provided proper training on operating heavy equipment that they use in their work. Summary:County roads’ chip sealing costs $20,000 per mile. An insufficient maintenance fund for the last 30 years has resulted in a maintenance backlog that amounts to approximately 12 million dollars.
No recommendations for this finding