📋
Extracted from Consolidated Report

This investigation was originally published as part of a larger consolidated report containing multiple investigations. View the consolidated PDF for the complete document.

San Francisco County Grand Jury • 2020-2021

Contracting and Preconstruction

11 pages
View PDF View Full Original

Findings 14 findings

F1 Page 19
The delays in completion of the Van Ness BRT Project were caused primarily by avoidable setbacks in replacement of the water and sewer infrastructure.
F2 Page 19
The potential impact of utility replacement on the cost and duration of the overall project was given insufficient consideration in the initial planning process.
F3 Page 19
The potential impact of utility replacement was known to City engineers to be a major risk but was only considered a moderate risk and assigned no mitigation strategy in the official risk register.
F4 Page 19
Project timelines could not be estimated accurately because documents did not reflect the extent and location of underground utilities accurately.
F5 Page 19
The evaluation rubric for preconstruction contract bids weighted cost too heavily, as compared to technical expertise, even after project-specific legislation allowed for a lower weight to be assigned to cost.
F6 Page 19
Practical work during preconstruction that could have derisked the subsequent construction phase of the project was insufficient.
F7 Page 19
Review of preconstruction deliverables did not sufficiently measure the contractor’s preparedness for construction, which resulted in both inaccurate cost estimates and timelines.
F8 Page 19
The effectiveness of the CMGC contract was greatly reduced because the general contractor was brought into the design process too late.
F9 Page 19
Underspecification in technical requirements led to additional costs for work that could have been predicted and included in the original contract.
F10 Page 19
Contention over underspecified or unclear contract terms and technical requirements led to a deterioration in the relationship between the City and Walsh, the general contractor.
F11 Page 19
The removal of Synergy, the underground subcontractor, from the project, partially as a result of poor cost estimates, contributed to the deterioration of the relationship between Walsh, the general contractor, and the City.
F12 Page 19
The contentious relationship between Walsh, the general contractor, and the City made it difficult to resolve problems as they arose, despite close collaboration being one of the potential advantages of the CMGC contract.
F13 Page 19
Lack of an in-the-field point of contact between Walsh and the City during early stages of construction led to delays and increased costs on the project. 19
F14 Page 20
Confusion related to the contractual requirements for pedestrian monitoring contributed to the deterioration of the relationship between Walsh, the general contractor, and the City.

Recommendations 12