Extraído del Informe Consolidado

Esta investigación fue publicada originalmente como parte de un informe consolidado más amplio que contiene múltiples investigaciones. Consulte el PDF consolidado para ver el documento completo.

Calaveras County Grand Jury • 2018-2019

Community College Districts

11 pages
View PDF View Full Original

Findings 5 findings

F1 Page 45
Measure L Bond language implied that a Foothills campus would be built by SJDCD. After the Bond was approved by SJDCD voters, the project was abandoned, and there are no plans to build a campus or a college learning center in Calaveras County for the remaining life of the Bond.
F2 Page 45
Despite the BOS response to the 2013-2014 CCGJ report which expressed their desire for SJDCD to expand and establish a Foothill area campus or education center, this has not occurred and will not occur during the life of the Bond.
F3 Page 46
According to the SJDCD 20-Year Comprehensive Master Plan, the District will likely require the passage of another bond measure to fund its long-term capital expenses for construction and improvements.
F4 Page 46
As long as Calaveras County is a member of SJDCD, any new bond could be approved with or without the support of County voters.
F5 Page 46
There is a strong desire among Calaveras County educators and students for higher education opportunities within the County.

Recommendations 5