Orange County Grand Jury • 2016-2017

Required Responses

14 pages
View PDF View Full Original

Findings 3 findings

F3 Page 25
Approval of OCTA as implementer and owner/operator of the OC Streetcar Project, and as subsequent grantee for the Federal New Starts Program, has created the basis for enabling further light rail development in Orange County to include public outreach and marketing/promotion efforts.
F4 Page 25
Creation by OCTA of a draft light rail Master Plan for Orange County that includes both intra and inter county transit connectivity options would be of considerable value to the public.
F5 Page 25
The long project times associated with light rail system establishment require not only careful planning and coordination by OCTA, but also consistent efforts to inform the public by those Orange County cities involved in development or possible development of light rail projects. RECOMMENDATIONS In accordance with California Penal Code Sections 933 and 933.05, the 2015-2016 Grand Jury requires responses from each agency affected by the recommendations presented in this section. The responses are to be submitted to the Presiding Judge of the Superior Court. Based on its investigation titled “Light Rail: Is Orange County on the Right Track?” the 2015- 2016 Orange County Grand Jury makes the following eight recommendations:

Recommendations 8