F1
The subpoena process took an addiƟonal four - six weeks to complete and schedule interviews with City Officials.
F2
The subpoena process took an addiƟonal four - six weeks to complete to obtain documents.
F3
A former interim city manager did not respond to a subpoena request for interviews. Four of the elected officials did not show for their iniƟal scheduled interview. The Civil Grand Jury had to reissue subpoenas for those interviews.

Recommendations 5