This investigation was originally published as part of a larger consolidated report containing multiple investigations. View the consolidated PDF for the complete document.
Wayne Brown Correctional Facility Reason for Investigation*
⚠️ Translation Notice: This content has been automatically translated. The original English text is the official version. Translation may contain errors.
⚠️ Este contenido ha sido traducido automáticamente. El texto original en inglés es la versión oficial. La traducción puede contener errores.
Findings 14 findings
Recommendations 7
-
R1The Grand Jury recommends that staffing needs and funding be identified and obtained in order to screen all visitors entering the courthouse. The Grand Jury recommends that electronic surveillance equipment be purchased and installed in the
-
R2courtrooms and hallways of the building. The Grand Jury recommends the BOS direct the County Administrative Officer to develop a written procedure to assure that future delays caused by lack of planning are eliminated in completing any projects REQUIRED RESPONSES Sheriff Due August 31, 1999 Board of Supervisors Due September 30, 1999 County Administrative Officer Due August 30, 1999 6
-
R3The Grand Jury found that some of the critical improvements to the Substation had not been accomplished since the 1997-98 Grand Jury report on the Truckee facility was released. At the time of our investigation, the Truckee Substation Jail was not open full time due to a shortage of jail staff. The jail will not reopen on a full time basis until a minimum staff of six correctional officers is b assigned to comply with BOC standards.
-
R4On September 23, 1997, a BOC field representative, in a letter to the Assistant Sheriff, made several recommendations regarding the Truckee Substation. Some of these recommended changes which have not been made are: 7
-
R5The Grand Jury researched why the needed changes to the Truckee Substation had not been completed. The list below is in chronological order: 9-23-97 letter from BOC field representative to Assistant Sheriff describing required upgrades to the Truckee substation 9-30-97 letter from a construction firm to Sheriff's office with a detail bid on some requested • work including new fire doors and new dividing walls 10-9-97 electrical company bid on electrical and surveillance equipment needed for the • substation 10-24-97 electrical company bid on dispatch area 10-30-97 safety inspection report by the office of the State Fire Marshall on the Truckee 0 Substation calling for needed repairs to the fire alarm system 11-04-97 work order from an electronic systems company for work on the fire alarm and related 0 systems 11-18-97 letter from Office of the State Fire Marshall, in a follow up inspection, that the fire alarm system was operational and "fire watch" conditions were no longer necessary 11-19-97 letter from Deputy State Marshall, Department of Forestry and Fire Protection to . facility captain requesting immediate attention to several issues including electrical, fire alarm system and inoperable exit door 12-11-97 letter from Assistant Sheriff to Facilities Management of Nevada County requesting changes and improvements needed to upgrade the Truckee Substation 3-31-98 construction bid on framing, electrical, sheet rock work, doors, hardware and flooring in 8 dispatch area 4-02-98 second bid on same work 6-19-98 e-mail from Truckee Dispatcher to Commander, Truckee Substation notifying of an electrical failure in the dispatch and 911 center the previous night 8-12-98 through 8-31-98 eleven e-mails between Sheriffs Department, General Services Department and County Risk Manager discussing unsafe working conditions and funding for proposed corrective work 8-31-98 e-mail between Sheriff's Department and General Services Department discussing placement and prices of equipment, including discussion of why plans or specifications are not available 9-15-98 e-mail from Commander, Truckee Substation to Assistant Sheriff discussing diagrams of proposed changes and discussed Grand Jury visit and the Grand Jury's dismay that work requested in 1997 had not even been started 8 9-17-98 letter from County Risk Manager to Sheriff again describing the electrical problems at . the Truckee Substation 9-25-98 e-mail from Assistant Sheriff to Director, General Services asking why the Sheriff's . office is required to define equipment and installation 9-25-98 five more e-mails between the Truckee Substation Commander, the Sheriff's office and General Services on the above issues with no apparent action 10-08-98 e-mail Sheriff's Department to General Services Department about budget transfer of $10,000 for Truckee Substation project 11-03-98 three e-mails, from Sheriffs Department, General Services Department and dispatch • manager of the Truckee Substation, the first discusses the need for Board of Supervisors (BOS) approval. The other two discuss the deplorable work environment at the Truckee Substation. A remodel that had started September 21, 1998 only included American Disabilities Act requirements. This resulted in a hazardous dispatch /911 work area because wiring and exposed flooring had not been properly completed. 11-10-98 Nevada County Board of Supervisors (BOS) minutes, (volume 58, pages 371 through . 373) discusses repairs to the Truckee Substation. This discussion included dollar amounts placed on projects keeping them below County and State mandated levels, to expedite certain purchasing contracts without the necessity of either formal bidding and/or BOS approval. Government Code Section 25500 authorizes a county to employ a Purchasing Agent. If such is done, competitive bidding requirements are generally dispensed with within the area of the Purchasing Agent authority. The State mandated level is below $6500 and the County level is below $10,000.
-
R6The Grand Jury found on 12-29-98 during their visit to the Truckee Substation that some of the work projects as per BOC requirements dated 9-23-97 were close to completion. The surveillance and security equipment arrived at the Nevada County Purchasing Department on or about January 29,
-
R7The Sheriff's Department should request the CAO to conduct a study to determine an entry pay rate that would attract viable candidates for deputies and correctional officers. 16
Conclusions 2
-
CL1 Page 2The Sheriff's Department has made significant progress in correcting problems identified by previous Grand Jury recommendations at the WBCF.
-
CL2 Page 2The staff employed at WBCF perform their work in a professional manner.
* This report's PDF did not contain easily extractable text and required Optical Character Recognition (OCR) for analysis. There may be minor errors in the extracted findings and recommendations due to OCR limitations with scanned documents.