Sutter County Grand Jury • 2019-2020

City of Live Oak - Public Works, Project Delivery

24 pages
View PDF View Full Original

Findings 4 findings

F2 Page 57
The City of Live Oak has not provided consistent explanations for work delays.
F3 Page 57
There is a lack of responsibility and accountability by the City of Live Oak management.
F4 Page 57
There is a lack of oversight by Live Oak City Courcil.
F5 Page 57
_ Lack ofoversight and project management has caused delays and cost overruns, as well as, impacts to other systems and projects. RECOM]TIENDATIONS Rl. Live Oak City Council to direct the City Manager to provide the following: . Quarterly report ofprojects to the Live Oak Council, starting by September 2020. o To restart the Water, Sewer and Storm Drain Committee meetings on a quarterly basis. o Quarterly report on the Water, Sewer and Storm Drain Committee meetings/activitie s to the Live Oak Council.

Recommendations 3