F1 Page 19
the status of Measure C funds is tracked and monitored by the Kern Community College District (KCCD) and Kern County. The fund balance as of 6/30/12 was over $8,000,000, with $4,000,000 remaining bonds to be issued. The account is audited annually by an external auditor.
No recommendations for this finding
F2 Page 19
the summary spreadsheet and detailed spreadsheet track Measure C expenditures over the years very clearly. Due to the length of time since initial construction, the main facility will need structural maintenance in the future. Currently this is not tracked separately from construction.
No recommendations for this finding
F3 Page 19
three studies have been completed since the passage of the bond measure in 2000, addressing facilities and programming needs. The Director of the Eastern Sierra College Center (ESCC), working with the KCCD Chief Financial Officer and the Facilities Committee determine facilities priorities appropriate for Measure C funding.
No recommendations for this finding
F4 Page 19
the ESCC Director works very closely with the Executive Director of the Mammoth Lakes Foundation (MLF) to gain community input and financial support for the Mammoth Campus of the ESCC.
No recommendations for this finding
F5 Page 19
enrollment growth projections dropped dramatically after passage of the bond, and as a result the current facility is now underutilized. Some of the classrooms are being “repurposed” and improved, and as appropriate, some Measure C funding may be used.
No recommendations for this finding
F6 Page 19
Facilities’ planning is current and takes into account the drop in enrollment projections over the past twelve years.
No recommendations for this finding
F7 Page 19
the first ESCC “2011 Report to the Community” does not contain information concerning Measure C and what has been constructed as a result of the bond measure.