20 responses to findings and recommendations
F1
Charles M. Schultz - Sonoma County Airport’s failure to update and execute its Master Plan in compliance with FAA recommendations is a root cause of airport maintenance and development problems.
Response: Agree
Score: +1
agree with the findings numbered: F1, F2, F3, F6, F8, F9 I (we) disagree wholly or partially with the findings numbered: F4, F5, F7 (Attach a statement specifying any portions of the findings that are disputed with an explanation of the reasons.
F2
STS’s current management resources are more appropriate for a general aviation or small commercial airport than for the medium sized passenger airport that Sonoma County Airport has become.
Response: Agree
Score: +1
agree with the findings numbered: F1, F2, F3, F6, F8, F9 I (we) disagree wholly or partially with the findings numbered: F4, F5, F7 (Attach a statement specifying any portions of the findings that are disputed with an explanation of the reasons.
R2
stand-alone agency and will forward an appropriate recommendation to the Board of Supervisors. By December 1, 2025, the County Executive Officer will evaluate the need for engaging a qualified Airport Master Plan consultant as suggested in FAA Advisory Circular (AC) 150/5070-
Response: Unknown
Score: 0
R2, R3, R4, R5, R6, R7, R8, R9, R10, R12, have not yet been implemented, but will be
R13
implemented in the future.
F3
Sonoma County Airport’s management is reactive rather than proactive due to inadequate resources and staffing.
Response: Agree
Score: +1
agree with the findings numbered: F1, F2, F3, F6, F8, F9 I (we) disagree wholly or partially with the findings numbered: F4, F5, F7 (Attach a statement specifying any portions of the findings that are disputed with an explanation of the reasons.
R3
6B to facilitate a comprehensive review of the Charles M. Schultz-Sonoma County Airport Master Plan. By June 1, 2026, Sonoma County Airport shall complete and publish a full update of the Airport Master Plan using the most current version of FAA Advisory Circular (AC) 150/5070-6B to
Response: Unknown
Score: 0
R3, R4, R5, R6, R7, R8, R9, R10, R12, have not yet been implemented, but will be
R13
implemented in the future.
F4
Sonoma County Airport projects compete with road repair, traffic management, purchasing and other projects for senior Public Infrastructure Department leadership attention.
Response: Agree
Score: +1
agree with the findings numbered: F1, F2, F3, F6, F8, F9 I (we) disagree wholly or partially with the findings numbered: F4, F5, F7 (Attach a statement specifying any portions of the findings that are disputed with an explanation of the reasons.
R4
guide requirements for completing the updated plan.
Response: Unknown
Score: 0
R4, R5, R6, R7, R8, R9, R10, R12, have not yet been implemented, but will be
R13
implemented in the future.
F5
Parking is the largest airport revenue source, but the absence of adequate parking on site is a material barrier to continued growth. June 2025 11 Sonoma County Civil Grand Jury Sonoma County Airport
Response: Agree
Score: +1
agree with the findings numbered: F1, F2, F3, F6, F8, F9 I (we) disagree wholly or partially with the findings numbered: F4, F5, F7 (Attach a statement specifying any portions of the findings that are disputed with an explanation of the reasons.
R5
inspection self-certification, and use of program management techniques to fulfill all Berry Dunn Report recommendations. By December 19, 2025, Permit Sonoma shall review and publish an accurate update to its January 2025 Board of Supervisors report on progress toward fulfillment of the Berry Dunn
Response: Unknown
Score: 0
R5, R6, R7, R8, R9, R10, R12, have not yet been implemented, but will be
R13
implemented in the future.
F6
Sonoma County use of airport land for non-airport purposes without paying rent could expose the County to significant FAA penalties.
Response: Agree
Score: +1
agree with the findings numbered: F1, F2, F3, F6, F8, F9 I (we) disagree wholly or partially with the findings numbered: F4, F5, F7 (Attach a statement specifying any portions of the findings that are disputed with an explanation of the reasons.
R6
report recommendations. By March 27, 2026, Permit Sonoma shall determine whether additional resources are required to fully implement the workflow system upgrades needed to fulfill all Berry Dunn Report
Response: Unknown
Score: 0
R6, R7, R8, R9, R10, R12, have not yet been implemented, but will be
R13
implemented in the future.
F7
Other than compliance with California Assembly Bill 2234 (2022), Permit Sonoma senior management has not established objective expectations for staff performance regarding plan review or timely permit issuance.
Response: Agree
Score: +1
agree with the findings numbered: F1, F2, F3, F6, F8, F9 I (we) disagree wholly or partially with the findings numbered: F4, F5, F7 (Attach a statement specifying any portions of the findings that are disputed with an explanation of the reasons.
R7
recommendations and communicate such incremental budget requirements to the County Executive Officer and the Board of Supervisors. By March 27, 2026, Permit Sonoma will review, publish (and require consistent staff usage of) requirements checklists for issuance of all permit types.
Response: Unknown
Score: 0
R7, R8, R9, R10, R12, have not yet been implemented, but will be
R13
implemented in the future.
F8
Permit Sonoma does not provide information to the public about over the counter and express permit review requirements and opportunities in a manner that is easily accessible and comprehensive.
Response: Agree
Score: +1
agree with the findings numbered: F1, F2, F3, F6, F8, F9 I (we) disagree wholly or partially with the findings numbered: F4, F5, F7 (Attach a statement specifying any portions of the findings that are disputed with an explanation of the reasons.
R8
By March 27, 2026, Permit Sonoma shall review and update its workflow system training materials and protocols for all Permit Intake, Plan Check, and Planning personnel.
Response: Unknown
Score: 0
R8, R9, R10, R12, have not yet been implemented, but will be
R13
implemented in the future.
F9
Permit Sonoma permit intake and plan check staff need additional workflow systems training to ensure accurate data entry and consistent use of status reporting conventions.
Response: Agree
Score: +1
agree with the findings numbered: F1, F2, F3, F6, F8, F9 I (we) disagree wholly or partially with the findings numbered: F4, F5, F7 (Attach a statement specifying any portions of the findings that are disputed with an explanation of the reasons.
R9
By March 27, 2026, Permit Sonoma shall establish and publish, in a consistent format, standard operating procedures for all Planning, Building, Engineering, Well & Septic, and
Response: Unknown
Score: 0
R9, R10, R12, have not yet been implemented, but will be
R13
implemented in the future.
R10
Code Enforcement permit issuance/compliance review processes. June 2025 31 Sonoma County Civil Grand Jury Permit Sonoma 2025 By May 1st, 2026, the County Executive shall review Permit Sonoma’s resource requirement noted in Recommendation 7 for inclusion in the Board of Supervisors’ 2026-27 budget review.
Response: Unknown
Score: 0
R10, R12, have not yet been implemented, but will be
R13
implemented in the future.
R12
timeliness requirements of 2022 California Assembly Bill 2234. By July 13, 2026, or as soon thereafter as allowed by budget authority, Permit Sonoma shall implement workflow system upgrades sufficient to ensure that individual and collective
Response: Unknown
Score: 0
R12, have not yet been implemented, but will be
R13
implemented in the future.
R13
throughput performance is captured and reported in a reliable and consistent manner.
Response: Will Not Implement
Score: -1
implemented in the future. (Attach a timeframe for the implementation.) Recommendations numbered: R1______ require(s) further 0 analysis. (Attach an explanation and the scope and parameters of an analysis or study, and a timeframe for the matter to be prepared for discussion by the officer or director of the agency or department being investigated or reviewed, including the governing body of the public agency when applicable. This timeframe shall not exceed six months from the date of publication of the Grand Jury report.) Recommendations numbered: None____ will not be implemented because they...