San Diego County Grand Jury • 2013-2014

Don’t Give Me a Break Water Distribution Problems in the City of San Diego

Published: June 26, 2014 9 pages
Ver PDF original

Findings 7 findings

F01
Not all SDPUD first responders are state certified. Fact: The only map the SDPUD supplies its personnel is the Thomas Brothers Guide. Fact: The Thomas Brothers Guide provides no routing information. Fact: GPS devices are readily available, relatively low cost, and generally provide the best routing information to any point in the city. Fact: Emergency Service personnel who wish to use a GPS device must expend their own funds to purchase one.
F02
Emergency Service personnel could frequently get to a disruption of service faster if they possessed department supplied GPS devices. Fact: SDPUD first responders rely on a paper copy of the Water Field Book to locate valves. Fact: Updated editions of the Water Field Book are not published on a regular basis. Fact: Water Field Books used by some first responders are several years out of date. Fact: Up to date information on pipe and valve location is maintained by SDPUD in a computer data base called SPLASH. 8 “City of San Diego Public Utilities Department; Asbestos Cement Water Main Replacement Program; Master Plan (H125808)”, HDR/Schiff, January 2014 /2014 FINAL REPORT (June 26, 2014)
F03
First responders do not have access to the most up to date information, which may slow response time. Fact: SDPUD has a goal of shutting down all breaks within 30 minutes of a report. Fact: SDPUD does not record enough information to determine actual response times, and some of the information it does have is demonstrably inaccurate.
F04
SDPUD is not able to adequately judge its performance with its current record keeping process. Fact: The City has fewer than 80 miles of remaining Cast Iron pipes.
F05
SDPUD is on track to eliminate all remaining Cast Iron pipes. In fact, they are ahead of schedule. Fact: The City has approximately 2,120 miles of remaining asbestos cement pipe. Fact: The City stopped installing asbestos cement pipe approximately 30 years ago. Fact: At a replacement rate of 40 miles/year (far exceeding the current replacement capacity), it would take 53 years to replace the remaining asbestos cement pipe.
F06
In the unlikely event that SDPUD accomplishes a 40 miles/year replacement rate, replacement of even the newest asbestos cement pipe will be scheduled significantly beyond the end of its predicted service life. Fact: AC pipe is currently being replaced strictly on an emergency (i.e., break) basis. Fact: SDPUD is in a very early stage of planning for AC pipe replacement. They have authorized and received a report on the history and potential problems of AC pipe.
F07
SDPUD needs to aggressively speed up its planning for AC pipe replacement.

Recommendations 9

No Responses Found 1

Government entities assigned to respond to this report. No response documents have been linked in our database.

San Diego City