Orange County Grand Jury • 2020-2021

Grand Jury 2020-2021

Published: June 11, 2020 76 pages Consolidated Report
Ver PDF original

Findings and Recommendations 6 findings

F1
When the TCA completes the 91 Express Connector, its major necessary construction work will be finished.
No recommendations for this finding
F2
By focusing on bond payoff, the TCA could retire its debt by 2037.
No recommendations for this finding
F3
Based on the TCA's current debt repayment plan, the total cost of the toll roads will amount to $28 billion by 2053.
No recommendations for this finding
F4
The TCA can cover its debt obligations without the use of Development Impact Fees.
No recommendations for this finding
F5
Even when the TCA's debt is retired, the roads will likely not become toll-free.
No recommendations for this finding
F6
Maintaining two agencies creates cost inefficiencies and extends the amount of time required by SJHTCA to pay off its debt.
No recommendations for this finding

Commendations 1

Agency Responses 1

Government agencies' official responses to this report's findings and recommendations. Click on a response to see the structured breakdown.

No Responses Found 1

Government entities assigned to respond to this report. No response documents have been linked in our database.

Orange County Board of Supervisors Elected County Office