Score: +11 (11/6/0)
San Francisco County Grand Jury • 2020-2021

Van Ness Avenue: What Lies Beneath

30 pages Consolidated Report
View Original PDF

Findings 14 findings

F1
The delays in completion of the Van Ness BRT Project were caused primarily by avoidable setbacks in replacement of the water and sewer infrastructure.
F2
The potential impact of utility replacement on the cost and duration of the overall project was given insufficient consideration in the initial planning process.
F3
The potential impact of utility replacement was known to City engineers to be a major risk but was only considered a moderate risk and assigned no mitigation strategy in the official risk register.
F4
Project timelines could not be estimated accurately because documents did not reflect the extent and location of underground utilities accurately.
F5
The evaluation rubric for preconstruction contract bids weighted cost too heavily, as compared to technical expertise, even after project-specific legislation allowed for a lower weight to be assigned to cost.
F6
Practical work during preconstruction that could have derisked the subsequent construction phase of the project was insufficient.
F7
Review of preconstruction deliverables did not sufficiently measure the contractor’s preparedness for construction, which resulted in both inaccurate cost estimates and timelines.
F8
The effectiveness of the CMGC contract was greatly reduced because the general contractor was brought into the design process too late.
F9
Underspecification in technical requirements led to additional costs for work that could have been predicted and included in the original contract.
F10
Contention over underspecified or unclear contract terms and technical requirements led to a deterioration in the relationship between the City and Walsh, the general contractor.
F11
The removal of Synergy, the underground subcontractor, from the project, partially as a result of poor cost estimates, contributed to the deterioration of the relationship between Walsh, the general contractor, and the City.
F12
The contentious relationship between Walsh, the general contractor, and the City made it difficult to resolve problems as they arose, despite close collaboration being one of the potential advantages of the CMGC contract.
F13
Lack of an in-the-field point of contact between Walsh and the City during early stages of construction led to delays and increased costs on the project. 19
F14
Confusion related to the contractual requirements for pedestrian monitoring contributed to the deterioration of the relationship between Walsh, the general contractor, and the City.

Recommendations 12

Conclusions 1

Agency Responses 1

Government agencies' official responses to this report's findings and recommendations. Click on a response to see the structured breakdown.

No Responses Found 4

Government entities assigned to respond to this report. No response documents have been linked in our database.

San Francisco City
San Francisco County Board of Supervisors Elected County Office
San Francisco Municipal Transportation Agency Transit Authority
San Francisco Public Utilities Commission GSA - Lobos Other