Sacramento County Grand Jury Status Review: Del Paso Manor Water District

Published: November 05, 2021 8 pages
View Original PDF

Findings and Recommendations 5 findings

F1
The DPMWD Board of Directors has responded to and agreed with each of the eight
Related Recommendations (1)
R1
The DPMWD should complete in earnest a full analysis of the 2009 Water District Master Plan, as was the original intent of the HydroScience Engineering contract to complete a Master Plan Update. This should incorporate all short, mid, and long-range repair and replacement needs with well-defined costs.
F2
The DPMWD Board of Directors is meeting the requirements of the Ralph M. Brown Act and Public Records Act with regard to providing public meeting agendas, minutes, and board packets in a timely manner. They have also conducted Brown Act training, as recommended by the Grand Jury.
Related Recommendations (1)
R2
The DPMWD should continue to work with the Sacramento Local Agency Formation Commission to complete a new Municipal Service Review in 2022, in alliance with the timeline developed and provided to the Grand Jury.
F3
The Sacramento Local Agency Formation Commission has agreed to conduct a new Municipal Service Review in coordination with the DPMWD, providing a detailed timeline for completion in 2022.
Related Recommendations (1)
R3
The DPMWD should develop and publicize its own Action Plans with timeframes for the Municipal Service Review and Proposition 218 process to secure voter approval of necessary rate increases.
F4
The DPMWD Board of Directors has agreed to initiate a Proposition 218 process to address a rate increase for needed infrastructure improvements.
Related Recommendations (1)
R4
The DPMWD should develop a strategic communications planning effort to regularly interact with its ratepayers through a variety of direct outreach efforts to ensure constituencies are informed of actions and associated costs to ensure a safe water supply.
F5
Although the DPMWD Board of Directors has publicly agreed with the recommendations of the Grand Jury’s November 5, 2021 report, the District has only begun to publicly address the methodology it will undertake to determine the full extent of the costs to repair infrastructure and make necessary safety improvements. 5
Related Recommendations (1)
R5
In the absence of a meaningful response by local leaders and agencies, the DPMWD should look for opportunities at the state and federal levels for funding resources which might help to alleviate the financial hardships confronting its ratepayers.

Agency Responses 2

Government agencies' official responses to this report's findings and recommendations. Click on a response to see the structured breakdown.

No Responses Found 2

Government entities assigned to respond to this report. No response documents have been linked in our database.