8 responses to findings and recommendations
F1
The prisoners’ entrance door is rusting.
Response: Unknown
Score: 0
F1. The building exterior paint is peeling. Response to
R1
The prisoners’ entrance door should be repaired and painted.
Response: Will Implement
Score: +1
R1: The recommendation has not yet been implemented, but will be implemented in the future. General Services will complete painting the building exterior by April 30, 2004.
F2
The prisoners’ entrance wooden door frame is deteriorating.
Response: Unknown
Score: 0
F2. The parking lot surface is severely checked and cracked, and poses a potential danger to users and potential liability to the county. Response to
R2
The prisoners’ entrance door frame should be repaired.
Response: Will Implement
Score: +1
R2: The recommendation has not yet been implemented, but will be implemented in the future. A detailed topographic survey has been conducted of the parking lot together with the existing drainage structures. Improvement plans together with technical specifications are nearly complete with bid solicitation to follow. Repair and resurfacing of the parking lot is scheduled for completion Septembe
F3
The downspouts at rear of the building are not connected to the drainage field pipes. 148
Response: Unknown
Score: 0
F3. The parking lot directional markings contradict the parking lot traffic flow and are severely faded. Response to
R3
The downspouts at rear of the building should be reconnected to the drainage field pipes.
Response: Will Implement
Score: +1
R3: The recommendation has not yet been implemented, but will be implemented in the future. The parking lot together with drive will receive new striping (paint) as a component of the parking lot repair and resurfacing project as described in
F4
The rain gutters are full of leaves and pine needles.
Response: Unknown
Score: 0
F4 El Dorado County Board of Supervisors El Dorado County Department of General Services El Dorado County Department of Community Services Responses Required for Recommendations
R7
The cracks in the courtroom and office area walls should be repaired.
Response: Unknown
Score: 0
r 7, 2002; • Toured the facilities and grounds with the Assistant Director of the Senior Day-Care Center; • Were briefed on the Senior Day-Care operations, including transportation, food and programs; • Inspected the building and grounds; • Reviewed previous Grand Jury reports for year’s 1999/2000, 2000/2001 and 2001/2002 and found no findings or recommendations pertaining to this building. Background The Senior Day-Care Center provides, at a nominal cost, a much-needed day care facility for seniors. Similar to Child Day-Care, this is a place where the seniors who cannot be left without superv...