Extracted from Consolidated Report

This investigation was originally published as part of a larger consolidated report containing multiple investigations. View the consolidated PDF for the complete document.

Amador County Grand Jury • 2023-2024

Amador County Civil Grand Jury Final Report

Published: June 26, 2023 2 pages
View PDF View Full Original

Findings 13 findings

F1
The propane tank at Howard Park was installed in December of 2020, despite Ione City Ordinance 489 prohibiting its installation.
F2
A permit to install the propane tank was issued without all departmental approvals.
F3
Written policies and procedures for overseeing this public works project were not followed, which resulted in lack of adherence to state, county, and city regulations. City of Ione Propane Tank
F4
Turnover of the City Manager Position in 2020 contributed to policies and procedures not being followed, which contributed to the propane tank installation in violation of the City Ordinance. Continued City Manager turnover resulted in further delays in correcting the violation.
F5
The generator can be retrofitted from propane to liquid natural gas.
F6
A secure pipeline can be trenched and connected to the generator from the existing liquid natural gas meter.
F7
The propane tank was removed on April 18, 2023, more than two years after it was installed (December 2020) and over two years after the City Council acknowledged there was an issue (February 2021).
F8
There was inconsistent follow-up from City staff when citizens raised concerns.
F9
The Jail has already had days when capacity exceeded 116 (which is the capacity with the expansion) even with some inmates released early, while others who committed low-level crimes were not booked at all. 9 9 Amador County Jail
F10
After the current Jail expansion plan from SB 863, there will be no more room for future expansion on this location.
F11
Staff refused to say anything bad about their jobs, even when prompted. We observed during the tour that staff seem to like their jobs but are approaching burn out due to understaffing and expanded job duties such as janitorial tasks. It was noted in several prior Grand Jury reports that staff had a morale boost during the time of the AB 900 talk and the SB 863 expansion. However, as time passed with no expansion construction, staff vacancies have increased.
F12
The roof is over 20 years old and in need of replacement. There is a plan to get the roof fixed before the expansion project begins.
F13
The staff have been very knowledgeable and accommodating during the tour and with all of our follow-up questions.

Recommendations 5

No Responses Found 1

Government entities assigned to respond to this report. No response documents have been linked in our database.

Ione City