Findings 6 findings

F1 Page 93
The first public announcement of the cost and schedule of an approved project is an initial estimate, which is usually lower than the eventually approved budget for the project based on the building contract costs and similar factors.
F2 Page 93
Major factors contributing to the increase in final cost/completion over original estimates include the passage of time between initial estimates and the execution of project contracts, changes in the cost of funds, late-discovered need for changes of design, unavailability of necessary materials, unexpected construction/labor problems, and changes in relevant regulations.
F3 Page 93
The reporting of final project completion sometimes includes statements that give rise to speculation that projects are not well managed. 2016-2017 San Luis Obispo County Grand Jury Final Report 82 Challenges in County Capital Projects
F4 Page 94
California law imposes detailed process requirements on all counties awarding building contracts for capital projects, with the clear intent of eliminating the possibility that anyone could allege bias, nepotism, or preferential treatment in the awarding of any public contract.
F5 Page 94
As the state authorizes it and as the County proposes to use it, the Design-Build project delivery method has generally proven in practice to expedite project completion and enable more cost-effective contracting with less financial and other risk to the owner.
F6 Page 94
While experts generally indicate that the Design-Build method can be useful for all types and sizes of projects, under California law there is a limit: If County policy permits, the County may use Design-Build for any vertical project with a price tag that will exceed one million dollars.