El Dorado County Grand Jury • 2003-2004

South Tahoe Redevelopment Agency

View PDF View Full Original

Findings 5 findings

F1 Page 40
There was poor oversight of the activities and inadequate financial management of the Park Avenue project. This was due to the same people serving on the city council and on the STRDA. Also there was high turnover of these elected official and their supporting city staff. 2003/2004 El Dorado County Grand Jury Investigations & Reports 30
F2 Page 41
The financial reporting system in use in the City of South Lake Tahoe during the years in question (1999-2002) was difficult to understand. There was a lack of notification and/or control in certain situations when overspending occurred. The City Council did not receive cogent, on-going spending updates as each year progressed.
F3 Page 41
The financial documents that the City Council received were difficult to understand and were not presented on a regular basis. These non-user friendly financial documents contributed to a lack of financial control over the project by the city council.
F4 Page 41
The same auditor was used by the city for several years.
F5 Page 41
The STRDA audit report dated 9/30/01 clearly identified a large deficit in the their fund. Nevertheless, no action was taken by staff or elected officials to memorialize the deficit in a loan agreement as required by the Cooperation Agreement.

Recommendations 12