Ventura County Grand Jury
• 2024-2025
Water Rates for the City of Ventura and the Underground Dam in Foster Park
⚠️ Translation Notice: This content has been automatically translated. The original English text is the official version. Translation may contain errors.
⚠️ Este contenido ha sido traducido automáticamente. El texto original en inglés es la versión oficial. La traducción puede contener errores.
Findings and Recommendations 3 findings
F01
The Civil Grand Jury finds that the incomplete underground dam in Foster Park has resulted in a 300-foot gap at the east end, allowing a significant amount of groundwater to flow through.
No recommendations for this finding
F02
The Civil Grand Jury finds that the amount of water produced from the Ventura River for use in Ventura has decreased from one-third of the total demand before 2004 to only 10% in 2021, due to drought, flood damage to wells and water intake facilities, and litigation aimed at protecting fish habitat.
No recommendations for this finding
F03
The Civil Grand Jury finds that the consultant for the 2021 Water Rate Study assigned all available water from the Ventura River to the rate calculation, resulting in the lowest possible water rate. Since dam construction will not be completed for some time and the rate study is currently underway, the improved river water production expected from the completion of the dam, which could benefit the water rate, will not be reflected in the ongoing rate study process. RECOMMENDATIONS
No recommendations for this finding
Agency Responses 1
Government agencies' official responses to this report's findings and recommendations. Click on a response to see the structured breakdown.
No Responses Found 2
Government entities assigned to respond to this report. No response documents have been linked in our database.
San Buenaventura
City
Ventura River Water District
Special District