Extracted from Consolidated Report

This investigation was originally published as part of a larger consolidated report containing multiple investigations. View the consolidated PDF for the complete document.

Los Angeles County Grand Jury • 2005-2006

Jails Committee / Detention Facilities

Published: June 06, 2006 26 pages
View PDF View Full Original

Findings 2 findings

F2 Page 111
Approve interior demolition including hazard material removal
F3 Page 111
Authorize contract documents for actual construction design. Taxpayer dollars are being wasted. Construction costs rise and the County has dragged its feet for 12 years. While projects are explored and scrapped (at great cost), the value of the $16 million FEMA Grant is greatly diminished. Projections today for refurbishing the HOJ are in the $200 million range. Each year all of the above costs are growing. THE COUNTY MUST MOVE FORWARD TO FORMULATE A PLAN AND ACT ON IT IMMEDIATELY.

Recommendations 4