Findings 3 findings

F1 Page 18
The boring samples were not taken from the area of the excavation where the sewer line was to be installed.
F2 Page 18
Performance of additional boring along the relocated pipeline and utilization of Dig Alert in the early stages of the project would have identified the concrete highway beneath the asphalt and the additional utility crossovers. Incorporation of this information into the initial bid documents would have eliminated the necessity of returning to the Board of Supervisors for the excessive overrun cost of the allocated budget.
F3 Page 18
Accurate drawings were not available identifying crossover utilities.

Recommendations 4