F1 Page 66
The costs of running the CWD exceed the revenue and must be supplemented with reserve funds.
F2 Page 66
The computers are very old and need replacing.
F3 Page 66
It is not economically feasible to have generator backup power available to run the pumping equipment in the event of a prolonged power outage.
F4 Page 66
If more customers were to come onto District water, it would help the overall budget.
F5 Page 66
Finding new customers is difficult as the District is still using “old school” methods of advertisement. 2019-2020 Tehama County Grand Jury Final Report 65