Nevada County Grand Jury • 2004-2005

Lessons Learned Reason for Investigation Citizens have voiced concerns and newspaper articles have reported on

7 pages
Ver PDF original

Findings and Recommendations 10 findings

F1
From September 2001 to March 2002, activities took place in the community to discuss the Bond election. The District Facility Improvement Plan and drawings were used to promote Measure A in many of these informational meetings.
No recommendations for this finding
F2
The District plan showed the placement of the competition pool and performing arts building located on the recently acquired ten-acre parcel fronting Magnolia Road. However, cost estimates were based on construction of the competition pool being on the existing campus adjacent to the gym.
Related Recommendations (1)
R4
The District should sponsor and conduct studies and public forums to plan any future expansion of needed facilities. Meetings pertaining to BRHS should address appropriate use of the ten-acre parcel on Magnolia Road.
F3
The ballot and proposition language of Measure A for improvements at BRHS stated, construct and furnish an addition to BRHS, including a new performing arts building and aquatic center. The budget in the District Facility Improvement Plan however, identified the improvements as pool facility, competition pool, community pool, aquatic center, performing arts auditorium and performing arts theater.
Related Recommendations (1)
R1
The Nevada Joint Union High School District (District) should ensure that future campaign information presented to the public is supported by accurate, comprehensive and complete data.
F4
Of the $15 million provided by Measure A, $7 million was allocated to construct and furnish an addition to Bear River High School, including a new performing arts building and aquatic center.
No recommendations for this finding
F5
After the voters approved Measure A, District officials learned that finishing the BRHS project on the ten-acre parcel could cost as much as $2 million more than budgeted. These costs were largely due to extensive grading and the compliance requirements in the Americans with Disabilities Act. The District made the decision to locate the competition pool and performing arts building to the rear of the existing campus. This action had been recommended by the design committee on October 21, 2002. Announcement of the relocation occurred at a public forum in February, 2003.
Related Recommendations (1)
R3
The District should heed the lessons learned in this episode, applicable to new construction on any campus and be more thorough in estimating construction costs, especially when the data are for use in supporting a bond election.
F6
The project design committee requested the District place a job sign on site to inform the community of the project s progress. This did not occur.
Related Recommendations (1)
R2
The District should alleviate misunderstandings with the community by making a greater effort for full, open and timely communications.
F7
The District was aware of previous lead deposits at the site found during the construction of the library prior to 2002. The levels were within the safety requirements set by the Department of Toxic Substances Control in effect at that time. New and more stringent standards resulted in the required removal of lead contaminated soil at the performing arts building site and arsenic contaminated soil found in test borings at the competition pool site.
No recommendations for this finding
F8
From the date of the Measure A Bond proposal to present, the District has experienced top level administrative turnover.
No recommendations for this finding
F9
Construction of the performing arts building was finally initiated in March 2005 with completion expected in 15 months. Construction of the competition pool is anticipated to begin in May 2005 with completion expected in 9 months. The facilities will be available to the public when not in use for school activities and outside of school hours.
No recommendations for this finding
F10
The Grand Jury was unable to locate the District s Bear River High School Master Plan. CONCLUSIONS
Related Recommendations (1)
R5
The District should ensure that there is a current Master Plan for Bear River High School that includes the ten acre parcel. RESPONSE REQUIRED Nevada Joint Union High School District Board of Trustees June 20, 2005

Conclusions 8

No Responses Found 1

Government entities assigned to respond to this report. No response documents have been linked in our database.

Nevada Joint Union High School District School District