11 responses to findings and recommendations
F1
The cost of replacing the track and football fields with synthetic all-weather materials at El Dorado, Oak Ridge, Ponderosa, and Union Mine high schools was $10,018,000.
Response: Agree
Score: +1
The EDUHSD agrees with Finding 1.
R1
The Grand Jury recommends the EDUHS District arrange a meeting within sixty (60) days from the publication of this report. Representatives from all involved parties are to work out a remediation action plan to fix the field depressions. This meeting should include at least the following parties: • Roebbelen Construction, Project General Contractor • Beales & Alliance, Project Architects • Joe Vicini, Inc., Project Grading Contractor • FieldTurf Company, Turf Installation Contractor • Representat...
Response: Implemented
Scheduled: within 60 days
Score: 0
The recommendation has been implemented. The EDUHSD has met with the parties involved in the design and construction of the Ponderosa track and field, in order to evaluate and discuss the condition of the field, in an effort to clarify the Grand Jury's findings. An electronic 3D image of the field will be prepared by the contractor with the use of lasers to fully assess the current condition of the field. The EDUHSD will use this information to monitor changes in the condition of the field and in potential discussions with safety experts, if such discussions appear necessary in the future. 2. ...
F2
At Ponderosa high school, the Grand Jury observed two rows of depressions on the football field’s surface running the length of the field. These depressions are located near the middle of the field and parallel to the hash marks.
Response: Disagree Partially
Score: 0
the middle of the field and parallel to the hash marks. The EDUHSD partially disagrees with Finding 2 because it gives the impression that there are two regular rows of depressions running the length of the football field.
R2
The Grand Jury expects that of the meeting the EDUHSD will report back to the Grand Jury with a plan including accountable parties, deadline dates and status update.
Response: Requires Analysis
Score: 0
The recommendation requires further analysis. The cause of the field's surface deflection is unclear and therefore establishing the accountable parties will be expensive (from a legal standpoint) and difficult at best. The EDUHSD will continue to monitor the field in conjunction with the contractor and others. 3. The Grand Jury recommends that the cost of this repair work not be paid with Measure Q monies, nor borne by the EDUHSD and its taxpayers.
F3
The other football field installed by the same contractor, Roebbelen Construction, was within speci- fied limits.
Response: Agree
Score: +1
The EDUHSD agrees with Finding 3.
R3
The Grand Jury recommends that the cost of this repair work not be paid with Measure Q monies, nor borne by the EDUHSD and its taxpayers.
Response: Requires Analysis
Score: 0
The recommendation requires further analysis. See
F4
Roebbelen representatives stated that the standard variance for artificial turf installation is 1/4” to level. Measurements were taken of the football field’s depressions and it was found that the west hash mark depression has a variance up to 7/8”. The east hash mark depression is slightly less, but still outside of the 1/4” variance in many places.
Response: Disagree Partially
Score: 0
The EDUHSD partially disagrees with Finding 4.
R4
The Grand Jury recommends that EDUHSD adopt a policy to ensure that completed capital projects are reviewed for proper standards and contract compliance. RESPONSES Responses to both findings and recommendations in this Report are required by law in accordance with California Penal Code §933 and §933.05. Address responses to: The Honorable Suzanne N. Kingsbury, presiding judge of the El Dorado County Superior Court, 1354 Johnson Blvd., South Lake Tahoe, CA 96150. This Report has been provided to ...
Response: Will Not Implement
Score: -1
This recommendation will not be implemented because it is not warranted. The EDUHSD carefully reviews every capital project for proper standards and contract compliance. In this case, the final project complied with the design standards and with the contract at the time of completion. The EDUHSD, in conjunction with contractors and others, will continue to monitor the condition of the Ponderosa field, and will have further inspections completed as needed to assure the safe condition of the field. Responses: 6. This Report has been provided to the EI Dorado Union High School District Board for ...
F5
The Superintendent stated the new field is better than the old grass field and that it would cost too much to fix the depressions. In a follow-up email, the Superintendent wrote that Ponderosa’s foot- ball field is inspected each year by the artificial turf’s company representatives, FieldTurf Company. The FieldTurf Company is aware of the depressions and has indicated that the depressions have not affected the field’s warranty.
Response: Agree
Score: +1
the depressions have not affected the field's warranty. The EDUHSD agrees with Finding 5.
F6
A member of the EDUHSD Board stated that the Board was advised of these depressions only after the initiation of this Grand Jury investigation. However, the Grand Jury learned that the district was notified three years ago about the field’s depressions during the installation of artificial turf at Pon- derosa’s football field. At that time mitigation efforts were undertaken to address depressions that developed in the field’s drainage trenches. The mitigation work that was done was to remove the...
Response: Disagree Partially
Score: 0
The EDUHSD partially disagrees with Finding 6.
F7
Ponderosa High School staff indicated that students have tripped while using the field during school hours. EVALUATION OF FINDINGS Measure Q bond monies totaling $10,018,000 were spent for the replacement of the track and football fields at the EDUHSD four high schools. Unfortunately, the depressions in the surface of the Ponderosa football field are a constant reminder to the taxpayers that they are paying for a potentially dangerous football field and nothing has been done to make it right. Th...
Response: Disagree
Score: -1
the field during school hours. The EDUHSD disagrees with Finding 7.